How to plan lead time for a concrete equipment order, from specification freeze to shipping and on-site commissioning.
Lead time starts with the specification
The clock starts only when the specification is frozen. Changes to silo count, mixer model or control system after fabrication begins can add weeks. Buyers who finalise the specification early consistently get faster delivery.
Long-lead components such as gearboxes, motors and load cells should be confirmed at order stage.
HAMAC concrete batching plant - 7.
Breaking down the schedule
A typical order runs through design confirmation, procurement of long-lead parts, fabrication, assembly and testing, then packing and shipping. Each stage has a duration, and they overlap only partly.
Sea freight and customs clearance are outside the factory's control and should be budgeted separately in the project plan.
Stage
Typical duration
Design confirmation
3-5 days
Long-lead procurement
10-20 days
Fabrication & assembly
15-25 days
Testing & packing
3-5 days
Sea freight
Varies by destination
Building in a buffer
Plan commissioning with a buffer for freight delay, weather and site readiness. The plant foundation and access roads are often the real cause of delay once the machine arrives.
HAMAC concrete batching plant - 9.
Need help applying this to your project?
Send your material type, target output and site conditions to HAMAC engineers. You will receive a practical equipment configuration and a clear quotation, normally within one working day.
Questions about this topic
When does lead time start?
When the specification is frozen and long-lead components can be ordered.
What causes the most delays?
Late specification changes, component availability, freight and site readiness such as foundations.
How can I shorten delivery?
Finalise the specification early, confirm component brands at order stage and prepare the site in parallel.
H
HAMAC Machinery Editorial Team
Written and reviewed by engineers and sales specialists who configure concrete batching plants, crushers, mixers and pumps for projects in more than 180 countries. Content is based on factory testing data and field feedback from delivered equipment.